IDB Bhaban-2

Background


Islamic Development Bank – Bangladesh Islamic Solidarity Educational Wakf (IsDB-BISEW) owns a land measuring 2(two) Acres at Agargaon Administrative Area, Sher-E- Bangla Nagar, Dhaka, Bangladesh. IsDB-BISEW decided to construct a Mixed-used Commercial Building Project (IDB Bhaban-2) which found to be commercially viable, financially lucrative as per feasibility study among various options.


The feasibility study also identified potential high-end multinational and international organizations, who have expressed their intention to lease the spaces of the IDB Bhaban-2 to setup their offices.


Meanwhile, CRCG-CCECC JV, a Chinese Joint Venture Company, has been engaged through international tendering process. Upon signing of the Contract on 31 July 2022, CRCG-CCECC JV mobilized adequate construction equipment and manpower at site and commenced the work under Tender Package-1 from 01 August 2022.


Progress of Work Versus Time Elapsed:


• Total Time : 36 Months


• Total % of Progress (up to March 2025) : 67.80%

Construction of IDB Bhaban-2 comprising of Multi-Storied Twin Tower and 4-Storied Multi-Purpose Business Center each with 3-Level Basements at Agargaon Administrative Area, Sher-e-Bangla Nagar, Dhaka.

Photo Gallary

Web-based Project Management System

  • Address
  • IDB Bhaban (4th Floor)
  • E/8-A, Rokeya Sharani, Sher-e-Bangla Nagar. Dhaka-1207, Bangladesh
  • +88 09638 917 000, +88 02223 374 601; Email: info@isdb-bisew.org

CRCG-CCECC JV Technical Team

CRCG-CCECC JV Technical Team

Mobilization of Equipment for Shore Piling Work

Site Visit by Hon’ble Chairman, COM. IsDB-BISEW

Checking Layout and Level

Drilling of Bore Hole for Pile by Hydraulic Rig

Site Visit by IsDB Group Members

Site Visit by IsDB Group Members

Site Visit by IsDB Group Members

Site Visit by Hon’ble Chairman, COM. IsDB-BISEW

Checking of Rebar Works for Reinforcement Caging of Shore Piles

Casting of Shore Pile


Site Visit by Hon’ble Chairman, COM. IsDB-BISEW

Reinforced Plaster Over Shore Pile

Earth Excavation at Level

(-) 7.0 M


Preparation of 75mm CC Casting under Footing


Wire Mesh Fixing to Shore Pile


75mm CC Casting under Mat Foundation over Damp Proof Membrane

Site Visit by Principal Structural Engineer

Applying Prime Coat for Water Proofing Membrane

Laying Water Proofing Membrane

Rebar Fabrication Work for Mat


Casting of Mat Segment -C of Business Centre

PVC Conduit Checking by Electrical Consultant


Casting of Basement-2 Slab


Water Logging in Berm Area during Heavy Rainfall – Steel Bracing Work above

Site Visit by Architect

1st Layer Bracing Work in North-South Side

Slab Casting of Ground Floor (Business Center)

Concrete Slump Checking at Site

Taking Cylinder During Casting at Site

Water Logging during Heavy Rainfall – Excavator Submerged

Reinforced Plaster Work along Shore Pile


Additional Bracing Work for Strengthening for Shore Protection at Segment-A

Checking of Sand Compaction Test (FDDA)


Bracing Work for Shore Protection

Business Center 1st Floor Casting (Central Part)

Brick work in Basement

South Side Retaining Wall Casting

2nd Layer Bracing Work in North Side

Sand Filling in Side Tranches

Site Inspection by Electrical Consultant


Video Gallary

Ongoing Superstructure Work for

Business Center & Twin Tower

Ongoing Superstructure Work for

Business Center & Twin Tower