
IDB Bhaban-2
Background
Islamic Development Bank – Bangladesh Islamic Solidarity Educational Wakf (IsDB-BISEW) owns a land measuring 2(two) Acres at Agargaon Administrative Area, Sher-E- Bangla Nagar, Dhaka, Bangladesh. IsDB-BISEW decided to construct a Mixed-used Commercial Building Project (IDB Bhaban-2) which found to be commercially viable, financially lucrative as per feasibility study among various options.
The feasibility study also identified potential high-end multinational and international organizations, who have expressed their intention to lease the spaces of the IDB Bhaban-2 to setup their offices.
Meanwhile, CRCG-CCECC JV, a Chinese Joint Venture Company, has been engaged through international tendering process. Upon signing of the Contract on 31 July 2022, CRCG-CCECC JV mobilized adequate construction equipment and manpower at site and commenced the work under Tender Package-1 from 01 August 2022.
Progress of Work Versus Time Elapsed:
• Total Time : 36 Months
• Total % of Progress (up to March 2025) : 67.80%
Construction of IDB Bhaban-2 comprising of Multi-Storied Twin Tower and 4-Storied Multi-Purpose Business Center each with 3-Level Basements at Agargaon Administrative Area, Sher-e-Bangla Nagar, Dhaka.
Photo Gallary
Web-based Project Management System
- Address
- IDB Bhaban (4th Floor)
- E/8-A, Rokeya Sharani, Sher-e-Bangla Nagar. Dhaka-1207, Bangladesh
- +88 09638 917 000, +88 02223 374 601; Email: info@isdb-bisew.org
CRCG-CCECC JV Technical Team
CRCG-CCECC JV Technical Team
Mobilization of Equipment for Shore Piling Work
Site Visit by Hon’ble Chairman, COM. IsDB-BISEW
Checking Layout and Level
Drilling of Bore Hole for Pile by Hydraulic Rig
Site Visit by IsDB Group Members
Site Visit by IsDB Group Members
Site Visit by IsDB Group Members
Site Visit by Hon’ble Chairman, COM. IsDB-BISEW
Checking of Rebar Works for Reinforcement Caging of Shore Piles
Casting of Shore Pile
Site Visit by Hon’ble Chairman, COM. IsDB-BISEW
Reinforced Plaster Over Shore Pile
Earth Excavation at Level
(-) 7.0 M
Preparation of 75mm CC Casting under Footing
Wire Mesh Fixing to Shore Pile
75mm CC Casting under Mat Foundation over Damp Proof Membrane
Site Visit by Principal Structural Engineer
Applying Prime Coat for Water Proofing Membrane
Laying Water Proofing Membrane
Rebar Fabrication Work for Mat
Casting of Mat Segment -C of Business Centre
PVC Conduit Checking by Electrical Consultant
Casting of Basement-2 Slab
Water Logging in Berm Area during Heavy Rainfall – Steel Bracing Work above
Site Visit by Architect
1st Layer Bracing Work in North-South Side
Slab Casting of Ground Floor (Business Center)
Concrete Slump Checking at Site
Taking Cylinder During Casting at Site
Water Logging during Heavy Rainfall – Excavator Submerged
Reinforced Plaster Work along Shore Pile
Additional Bracing Work for Strengthening for Shore Protection at Segment-A
Checking of Sand Compaction Test (FDDA)
Bracing Work for Shore Protection
Business Center 1st Floor Casting (Central Part)
Brick work in Basement
South Side Retaining Wall Casting
2nd Layer Bracing Work in North Side
Sand Filling in Side Tranches
Site Inspection by Electrical Consultant
Video Gallary
Ongoing Superstructure Work for
Business Center & Twin Tower
Ongoing Superstructure Work for
Business Center & Twin Tower